We have completed the underground plumbing and heating. The electrical will be completed before the slab is poured. The heat system is a "PCD" system. The heat will be forced air under the floor slab. That is the round pipe that you are seeing. Another view of the duct system. The slab will be poured on Tuesday and the framing will start soon after that.
|
|
|