January 4, 2003 - Roof Framing:  The dormer is framed and the roof is almost complete.  The entry is looking great!.

Montgomery-entry1    Montgomery-entry2    Montgomery-entry3    Montgomery-entry4-    Montgomery-frame1

The entry porch roof will be an open cathedral ceiling when you stand under it.  The face of the gable will be built as a wall and sided with vinyl shakes.

Monrtgomery-frame2    Montgomery-frane4    Montgomery-frame5-    Montgomery-frame6    Montgomery-frame7

The view into the living room from the second floor.  The trapizoids look nice and fit the room.  The ceiling will be a cathedral over the center of the tallest trap.

Montgomery-lakeside1    Montgomery-lakeside2

Lakeside.  Really nice.

Montgomery-pulldown1    Montgomery-pulldown2-    Montgomery-pulldown3

The pull-down stair.  The option for access to the area was limited at best.  This is the best solution in getting to the space.  The first picture is looking at the pull-down stair from the living room along side the stair to the second floor.

WoodCraft Home Page


January 1, 2003 - Framing:  The rafters are being placed and the main center beam is almost  set. We placed a temporary floor at the second floor to set our scaffold on to work on the beam.. 

Montgomery-entryframe1    Montgomery-entryframe2    Montgomery-entryframe3    Montgomery-beam1    Montgomery-beam2

The lakeside of the house is taking shape.

Montgomery-lakeframe1    Montgomery-lakeframe2    Montgomery-lakeframe3    Montgomery-trapz1-    Montgomery-trapz2-

The trapizoid glass openings at the living room have been framed.

Montomery-trapz3

Happy New Year!


December 27, 2002 - Framing:  We have started the roof framing with the roof rafters. 

Montgomery-deck1    Montgomery-deck2    Montgomery-deck3    Montgomery-framing2    Montgeomry-framing3-

The deck has started and the screen porch is taking shape.

Montgomery-framing4    Montgomery-framing5    Montgomery-framing6-    Montgomery-framing7    Montgomery-framing8

The bonus room above the master bedroom is very large and will make a great storage area.

Montgomery-framing10


December 21, 2002 - Framing:  The second floor level is on. The weather has been working with us and we have not had to much problem with the snow at this time.  The Flu that has been going around has not been so kind.

Montgomery-lakeside1    Montgomery-roadside1    Montgomery-floorframing1    Montgomery-framing10    Montgomery-framing11

The floor system is TJI engineered floor joist.

Montgomery-framing1    Montgomery-framing12    Montgomery-framing13    Montgomery-framing14    Montgomery-framing3

Main Floor framing.

Montgomery-framing4    Montgomery-framing5    Montgomery-framing6-    Montgomery-framing7    Montgomery-framing8-

Montgomery-framing9    Montgomery-grading1    Montgomery-grading2    Montgomery-grading3    Montgomery-lake-12

The grading has been done at the septic tank / field at the road edge.  This has filled in the depression that was at the side of the drive.

Montgomery-roadside2    Montgomery-roadside3    Montomery-roadside4-

WoodCraft Home Page


December 12, 2002 - Framing:  The main floor exterior walls are completed and the house is taking shape.

Montgomery-frame1    Montgomery-frame2    Montgomery-frame3    Montgomery-frame4-    Montgomery-frame5

Montgomery-frame6    Montgomery-frame7    Montgomery-frame8-    Montgomery-frame9-    Montgomery-frame10

 


December 11, 2002 - Framing:  The floor framing is complete and we are cutting all the components to build the main floor walls at this time.  The walls of the main floor should be completed in the next day.

Montgomery-bilco1    Montgomery-bilco2    Montgomery-deck1    Montgomery-deck2    Montgomery-deck3

Montgomery-deck5    Montgomery-eastline1    Montgomery-eastline2    Montgomery-septic1    Montgomery-lake

Montgomery-lakeside1    Montgomery-westline1

The lake is frozen over and Winter has begun.


WoodCraft Home Page